Evans Co-op Pumping Water Station

October 24, 2025

 

Completed August 2025

 

A gray water utility building with white shutters, a dark roof, and yellow posts. Set in a sunny, grassy area.

Evans Co-op Water Pumping Station Project – Epping NH


HAWSCO was contracted by Edgewater Strategies and CSA Environmental to completely replace the Water Distribution System and Build a complete new Water Pumping Station at the Evans Coop in Epping, NH.

 

The Distribution System portion consisted of installing roughly 1400 linear feet of new HDPE Water Mains, associated Gate Valves, all Curb Valves and new Service Connections to all existing 19 Units. The entire Coop was loamed and seeded in the affected areas and all roads were paved at the end of the Project.

 

The Pump House portion consisted of Building a 16’ x 26’ Wood Framed Building with Vinyl Siding, Wood Trusses and a Standing Seam Metal Roof from foundation to finish. The existing 10 HP Well Pump and piping were replaced and a stilling well and well level transducer were installed. Inside of the pump station there are two 2050 Gallon Storage Tanks that are filled by the Well. The Well water is treated by two greensand filters and an arsenic removal filter prior to filling the storage tanks. Two 3 HP 30 GPM Booster Pumps and all SCH 80 PVC Piping and Valves were installed for all water service to the distribution piping outlet connection. The booster pumps and instrumentation are automatically controlled by the RE Prescott Control Panel with user adjustable level, flow and pressure settings and multiple user configurable alarms with time delays and Web Based Portal alarm call out ability. The interior is automatically temperature controlled by a new HVAC System. The old existing Pump House was demolished and removed and the surrounding area was restored at the end of the Project.

 

This is another example of HAWSCO’s ability to safely deliver a top notch, turn key Project from start to finish on time and on budget.

gray water utility  building with shutters, dark roof, and yellow bollards on asphalt driveway
September 18, 2025
Completed August 2025
January 6, 2025
Completed December 2024
By HAWSCO February 23, 2024
The Bedford NH Pump Station is a Booster Station that provides Water for domestic use, irrigation and Fire Protection for a new development. HAWSCO performed all work from the Foundation up for a 22’ x 24’ CMU Building that is strapped and sided with Vinyl Siding, new 208 VAC Electric Service, a full HVAC System, REPCO Control System with full Instrumentation and Controls, and a 100 KW Natural Gas Generator.
By HAWSCO February 23, 2024
The Newmarket NH Tucker Well Project consisted of HAWSCO providing and installing a 40 HP 40VAC Submersible Turbine Well Pump complete with Casing Extension, Pitless Adapter and all accessories, providing and installing 7200 Linear Feet of 10” HDPE Water Main with all Hydrants and Gate Valves as required, all required Site Work and restoration for the Water Main installation as well as Drainage and Access Road installation to and from the Well, installation of the Town’s repurposed Generator with LP Tank and accessories, New 480 VAC Electric Service and Poles from the Road to the Station, as well as the Pump Station Building that houses all of the Electrical, Controls and Instrumentation and HVAC Systems complete.
East Road Booster Pump Station
By HAWSCO November 21, 2022
East Road Booster Pump Station HAWSCO is actively engaged with the Southern NH Regional Water Project (SNHRWP) and, as part of the overall project, completed the construction of this booster station in Plaistow, NH. The East Rd Booster station supplies water from the SNHRWP pipeline to the Town of Plaistow at a rate of up to 500 GPM filling the newly constructed 400,000 Gallon Water Tank on Sweet Hill Rd. HAWSCO constructed the Booster Station facility complete from the ground up including but not limited to site work, building construction, installation of the 2 Booster Pumps, all related piping, valves, instrumentation, sampling equipment and electrical control panels for the Town of Plaistow. There are two 20 HP Domestic Water Pumps that deliver 500 GPM each at 95’ TDH through 12” Ductile Iron Mains. This station is designed to automatically maintain programmed level setpoints in the Sweet Hill Water Tank with variable flows of 0-500 GPM through VFD’S and a SCADA Control System with a local SCADA control panel with a Touchscreen Operator Interface and remote SCADA PC’s with a fully programmable control system and alarm call out system.
Plaistow NH Water Tank Construction
By HAWSCO June 21, 2021
P3 – Plaistow NH Sweet Hill Tank Furnish and install a new 400,000 gallon Water Storage Tank Project complete with Valve Vault Building, connection to 12” Water Main, HVAC and Electrical Controls, Paving, Fencing and Site Restoration.
Bedford Booster Station
By HAWSCO February 3, 2021
Amidst a global pandemic in 2020, HAWSCO mechanically installed the 5 Booster Pumps, all related piping, valves, instrumentation, and control panel for the Bedford Assisted Living Facility Bowman Place.
Derry Booster Pump Facility Interior
By HAWSCO October 29, 2020
As part of the overall Southern NH Regional Water Project (SNHRWP) HAWSCO completed the construction of this 3,200 gallons per minute pumping station in Derry, NH.
Water Treatment Facility
By HAWSCO June 30, 2020
The Rockingham Road Booster Pumping facility is an integral component of the Southern New Hampshire Regional Water Interconnection Project, and with upgrades will now support the introduction of water to Salem’s, HAWC and ultimately the Plaistow water system.