Bedford NH Pump Station

The Bedford NH Pump Station is a Booster Station that provides Water for domestic use, irrigation and Fire Protection for a new development. HAWSCO performed all work from the Foundation up for a 22’ x 24’ CMU Building that is strapped and sided with Vinyl Siding, new 208 VAC Electric Service, a full HVAC System, REPCO Control System with full Instrumentation and Controls, and a 100 KW Natural Gas Generator.

The Newmarket NH Tucker Well Project consisted of HAWSCO providing and installing a 40 HP 40VAC Submersible Turbine Well Pump complete with Casing Extension, Pitless Adapter and all accessories, providing and installing 7200 Linear Feet of 10” HDPE Water Main with all Hydrants and Gate Valves as required, all required Site Work and restoration for the Water Main installation as well as Drainage and Access Road installation to and from the Well, installation of the Town’s repurposed Generator with LP Tank and accessories, New 480 VAC Electric Service and Poles from the Road to the Station, as well as the Pump Station Building that houses all of the Electrical, Controls and Instrumentation and HVAC Systems complete.

East Road Booster Pump Station HAWSCO is actively engaged with the Southern NH Regional Water Project (SNHRWP) and, as part of the overall project, completed the construction of this booster station in Plaistow, NH. The East Rd Booster station supplies water from the SNHRWP pipeline to the Town of Plaistow at a rate of up to 500 GPM filling the newly constructed 400,000 Gallon Water Tank on Sweet Hill Rd. HAWSCO constructed the Booster Station facility complete from the ground up including but not limited to site work, building construction, installation of the 2 Booster Pumps, all related piping, valves, instrumentation, sampling equipment and electrical control panels for the Town of Plaistow. There are two 20 HP Domestic Water Pumps that deliver 500 GPM each at 95’ TDH through 12” Ductile Iron Mains. This station is designed to automatically maintain programmed level setpoints in the Sweet Hill Water Tank with variable flows of 0-500 GPM through VFD’S and a SCADA Control System with a local SCADA control panel with a Touchscreen Operator Interface and remote SCADA PC’s with a fully programmable control system and alarm call out system.
The Westside Drive Water Treatment facility is a major component of the Southern New Hampshire Regional Water Interconnection Project, connecting water from Salem to Atkinson, Hampstead, and eventually Plaistow. As part of the connection, chloraminated water from the town of Salem will be introduced into the Hampstead Area Water Company, Inc.’s (HAWC) core water system. Treatment at this facility makes the water supplied by Salem compatible with HAWC’s existing water supplies. This facility will convert the existing type of disinfection (chlorine) to monochloramine within its existing water treatment process.

The Bedford NH Pump Station is a Booster Station that provides Water for domestic use, irrigation and Fire Protection for a new development. HAWSCO performed all work from the Foundation up for a 22’ x 24’ CMU Building that is strapped and sided with Vinyl Siding, new 208 VAC Electric Service, a full HVAC System, REPCO Control System with full Instrumentation and Controls, and a 100 KW Natural Gas Generator.

The Newmarket NH Tucker Well Project consisted of HAWSCO providing and installing a 40 HP 40VAC Submersible Turbine Well Pump complete with Casing Extension, Pitless Adapter and all accessories, providing and installing 7200 Linear Feet of 10” HDPE Water Main with all Hydrants and Gate Valves as required, all required Site Work and restoration for the Water Main installation as well as Drainage and Access Road installation to and from the Well, installation of the Town’s repurposed Generator with LP Tank and accessories, New 480 VAC Electric Service and Poles from the Road to the Station, as well as the Pump Station Building that houses all of the Electrical, Controls and Instrumentation and HVAC Systems complete.